Phase 1 Broadband

Posted on:
June 11, 2020

Victoria County has two areas that have been approved for an upgrade to current DSL standards. Bell was awarded the contract to provide Fibre to homes in Dingwall and Boularderie.

• Dingwall & Area is expected to be completed by April 21, 2021 or earlier
• Boularderie & Area is expected to be completed by June 21, 2021 or earlier

Wondering if your house is included in Phase 1? Check out the maps.

Dingwall & Area Community Maps

Boularderie & Area Community Maps

For more information, contact john.swantee@bellaliant.ca.